M&S Moortown
Overview Client: M&S Duration: 6 weeks (inc. 3 week store closure) Value: £1.2m As a highly trusted national Main Contractor to M&S, and with a proven track record of delivering major fit-outs and refurbishment projects and a detailed understanding of the demanding retail environment, Sigma’s expertise as end-to-end specialists was required to handle the complete […]
Boots World of Hearing

Overview Client: Boots Duration: Seven weeks – two years in the planning Value: £400,000 PC Date: 11th November 2022 Following the success of the work completed at the Chelmsford World of Hearing store, Sigma was contracted to provide a professional end-to-end solution at the Boots Guildford store. The turnkey scheme included providing a full design […]
Upgrading Air Handling Units

While retrofitting inverters in the old fans was possible, this would have been an expensive option and would not have delivered the desired improvements in energy efficiency. As a result, M&S decided to remove the existing belt-driven fan and motor assemblies within its air handling units and upgrade them with new energy-efficient, direct-drive EC plug […]
COOP M&E New for Old
New for old Client: Uplands Retail Ltd Location: Coop RDC Plymouth Services: Sigma M&E Before Sigma M&E could replace the generator and fuel tank system, it was imperative that the team installed, connected, tested, and commissioned a like-for-like standby generator to provide standby generation capability to the Distribution Centre in the case of a mains […]
Sigma delivers M&S equipment consolidation centre in UK

Bradford, UK, 22nd September 2022 Sigma, a true end-to-end solutions provider, and a leading expert at transforming commercial spaces, has secured a major multi-year contract to deliver a new 52,000 Sq. Ft , ‘best-in-class’ equipment consolidation centre (ECC), along with a 24/7 Transport Solution for Marks & Spencer (M&S), further extending its relationship with the […]
Modern Interior for M&S Cheltenham Store

Overview Client: M&S Duration: 5 weeks Value: £617K To improve the Cheltenham store for its customers, M&S extended retail space in the clothing department to accommodate new concessions and improve the layout, while refreshing the look of the whole store by adding digital screens, new signage and lighting fixtures. To bring the food hall up […]
Refurbishing ASDA Hounslow

Overview Client: Asda Hounslow Superstore Duration: 2 weeks As part of its commitment to customers, Asda regularly undertakes improvements to its stores in order to improve amenities and services and make them more convenient places to shop. Most recently, it decided to refurbish one of its superstores in the London Borough of Hounslow. The Brief […]
Marks & Spencer Upgrading Air Handling Units

Upgrading Air Handling Units This was an extensive transformation requiring work to be carried out on large numbers of air handling units across multiple sites. Sigma was commissioned to take M&S on the journey to improved efficiency by replacing over 200 fans across several of its stores. This involved removing the obsolete belt-driven fans and […]
Lidl Clifton Case Study

The Challenge Our role saw us manage multiple third parties and suppliers, implementing all construction aspects from wall linings, M&E and utility services to flooring, ceiling and decorating. We subsequently orchestrated the implementation of all interior fixtures and equipment, both in the front and back of house, delivering both a quality trading environment for customers […]
Incorporating a digital solution to the M&E fire damper survey project

Brief Client: M&S Scope: Initial trial of 150 stores, extended to 621 stores Duration: 12 months As part of the retailer’s commitment to ensure its safety systems are fully operational and fit for purpose, Sigma were tasked – following the successful completion of many planned maintenance schemes – with conducting inspection, testing and remedial works […]